delay on the first floor ...

09th July 2010

rested this week, unfortunately, all activities on site, because not enough material has been delivered to continue.
Unfortunately, hence the jamb not been completed, what can we fear that even the roof next week can not be fully established.

addition, the information that the wall ties are too short, has been confirmed by our quality inspectors and the construction manager. Thus there are two alternatives: first
It can be used for insulation, which requires less space for the same thermal insulation.
second All wall ties must be removed and replaced with longer ones.

In both cases, higher costs due to the shell, and we fear this further delay.
The positions of the Kaminzuluft and the chimney have not been corrected.

true All in all, our current situation very unhappy :-(

We hope that next week is in the one or two points for clarification and again to recognize progress will be.