Thursday, July 22, 2010

Images Of Warts On Scalp

Further delays in the floor ...

22nd July 2010

meantime are gone for another two weeks in which no progress can be seen in the construction. We continue to wait for the roof, which is, according to the carcass not available faster.
Until now we wait for 3 weeks that it :-(

goes After all, was finally cast in the last week of the jamb, so everything is ready for the roof.


















is now also clear that all wall ties are to be replaced is removed and replaced by new, longer wall anchor. The new wall anchors must be plugged so well is expected to substantial additional work by the shell.

The position of Supply air duct for the fireplace has now been corrected. However, this time was missed to make the necessary insulation to the base plate, so that may be re aufgestämmt.

... why can not simply listen, if such action is discussed. ?!?!?

The roof has now been promised for next week, we are see if it finally works.

Sunday, July 18, 2010

Tampax Vs. Kotex Vs. Playtex Project

flooding under the railway



came with 70 liters per square meter of the water from the sky yesterday. This creates the channels and not crossed. The result is water under the railway! And this morning by 1 clock :-( The fire department came to the room to suck. But the "rood screen" (clay / dirt) is natural.

Friday, July 9, 2010

Did Riven Riley Have Tatoo

delay on the first floor ...

09th July 2010

rested this week, unfortunately, all activities on site, because not enough material has been delivered to continue.
Unfortunately, hence the jamb not been completed, what can we fear that even the roof next week can not be fully established.

addition, the information that the wall ties are too short, has been confirmed by our quality inspectors and the construction manager. Thus there are two alternatives: first
It can be used for insulation, which requires less space for the same thermal insulation.
second All wall ties must be removed and replaced with longer ones.

In both cases, higher costs due to the shell, and we fear this further delay.
The positions of the Kaminzuluft and the chimney have not been corrected.

true All in all, our current situation very unhappy :-(

We hope that next week is in the one or two points for clarification and again to recognize progress will be.

Thursday, July 1, 2010

What Brand Of Glycerin Soap To Buy For Acne

The first floor continues to grow ...

July 01, 2010

Today we were able to gain an impression of the results of this week.















The Drempelmauerwerk is not yet complete because the concrete ring has not yet been poured. This is the Drempelmauerwerk until next week, and thus 2 weeks read on schedule.

Even with the delivery of the roof, a delay has been announced. Currently, states that the roof in the week after next, ie from 12 July is delivered.

Allow the topping must therefore also something coming.

addition, our quality assurance has to say today, that the wall ties have the requisite approval for the proposed insulation. Currently we do not know yet what to send to new problems for us.

small consolation: The inner wall and gable walls upstairs are already half completed, so we can get a first impression of the rooms.

... It will be exciting.