The first floor continues to grow ...
July 01, 2010
Today we were able to gain an impression of the results of this week.
The Drempelmauerwerk is not yet complete because the concrete ring has not yet been poured. This is the Drempelmauerwerk until next week, and thus 2 weeks read on schedule.
Even with the delivery of the roof, a delay has been announced. Currently, states that the roof in the week after next, ie from 12 July is delivered.
Allow the topping must therefore also something coming.
addition, our quality assurance has to say today, that the wall ties have the requisite approval for the proposed insulation. Currently we do not know yet what to send to new problems for us.
small consolation: The inner wall and gable walls upstairs are already half completed, so we can get a first impression of the rooms.
... It will be exciting.